The Kaduna–Zaria–Kano standard gauge railway project has reached about 90 per cent completion, with the Federal Government expressing optimism that the remaining works will soon be completed to enable seamless train services along the corridor.
According to a statement in Abuja on Friday, the Permanent Secretary, Federal Ministry of Transportation, Engr. Funso Adebiyi, disclosed this on Thursday while aboard a train ride from Jaji to Kano during an inspection of the project sites.
Adebiyi expressed satisfaction with the quality of work done, describing the rail alignment, embankment protection, drainage, stone-pitching and soil stabilisation works as excellent.
He said construction had largely complied with required specifications, stating: “I want to confess that the quality of work is next to none. The rail alignment apparently is excellent. When you look through the window, you see a sharp change in elevation, some as high as six metres, which tells you the volume of earthwork that is done. The embankment protection work is also great,” he said.
He explained that elevation differences of up to six metres or more along some sections underscored the importance of proper soil stabilisation, compaction and embankment protection for the railway’s safety and durability.
Adebiyi said he was delighted at the smooth train movement from Jaji towards Kano. “I am quite delighted. I feel excited. I don’t feel I should come out of this train, honestly,” he added.
However, he identified outstanding land acquisition and compensation claims within Kaduna metropolis as the major obstacle delaying completion of the remaining link between Jaji and the Abuja-Kaduna rail corridor.
He assured affected stakeholders that the government was addressing the issue and that it would receive immediate attention upon the team’s return to Abuja.
Adebiyi said President Bola Ahmed Tinubu was committed to completing the project as soon as possible, expressing optimism that passengers would soon travel uninterruptedly by train from Abuja through Kaduna and Zaria to Kano.
He said the inspected section covered approximately 145 kilometres of the broader 200-kilometre Kaduna-Kano route, with only about 10 kilometres of work remaining on the stretch.
He also disclosed that the railway sections extending from Kano through Kazaure and Daura to Katsina were targeted for completion by December, with work continuing round the clock to meet the deadline.
Speaking during the inspection, Director, Rail Transport Services in the Ministry, Engr. Habiba Buhari, said the exercise was intended to assess the technical quality of the infrastructure ahead of finalisation and test runs.
She said the team examined track geometry, alignment, drainage facilities, concrete works and other components relevant to passenger safety and comfort.
“We are here to check the geometry, the alignment, drainage facilities, quality of concrete works which we have been doing. We just want to finalise and test-run,” she said.
Buhari added that the exercise also provided an opportunity to engage stakeholders as the project approached completion.
The Kaduna-Kano railway is a major component of the Federal Government’s efforts to expand Nigeria’s rail network, strengthen connectivity between major commercial centres, improve passenger movement between the North-West and other parts of the country and provide an alternative to road travel.