The Bureau of Public Enterprises, acting on behalf of the Federal Government, is presently engaged in transactions for the sale of five power plants associated with the National Integrated Power Projects, totaling approximately $1.15 billion, according to sources on Tuesday.
While insiders with knowledge of the matter suggested that the plants’ value should exceed $5 billion based on international benchmarks, they disclosed that the BPE intends to sell the facilities at a slightly higher price, specifically above $1.1 billion.
Ignatius Ayewoh, the acting Director-General of BPE, confirmed in a brief telephone conversation with our correspondent that “the transaction is ongoing” but emphasized that “it is not concluded.” He did not disclose the specific cost for the five plants, citing ongoing discussions and mentioning that he was currently in a meeting.
However, credible sources at the bureau identified the five power plants as the 434-megawatt gas-fired Geregu II power plant in Kogi, the 451MW Omotosho II plant in Ondo, and the 750MW Olorunshogo II plant in Ogun State. The remaining two are the 563MW Odukpami power plant in Calabar, Cross River State, and the 451MW Benin-Ihovbor plant in Edo State.
The Omotosho plant, equipped with four power-generating turbines, is expected to be sold for around $85 million, while the Olorunsogo NIPP, also featuring four turbines, has an estimated cost of $170 million. The Benin-Ihovbor plant, boasting five power-generating turbines, is set to be priced at $420 million. The Calabar Odukpami plant, with five turbines, is projected to sell for approximately $260 million, and the Geregu plant, with four turbines, is valued at around $215 million.
“These are Siemens turbines and each of the turbine can generate about 115MW of electricity,” one of the sources, who pleaded not to be named due to lack of authorisation, stated.
The official went ahead to explain that it would cost about $1m to construct a plant that could generate 1MW of electricity, stressing that if the five NIPP plants were valued on this basis, they would cost more than $5bn.
It was, however, gathered that the cost of constructing 1MW power plant vary depending on several factors, including type of power plant, location, technological advancements, etc.
“But a general range for the cost of constructing a 1MW power plant based on different technologies is that for a solar power plant, it is between $1m to $2m per MW.
“For wind power plant, it is between $1.5m to $2.5m per MW. For natural gas-fired power plant, such as the NIPPs, it is between $1m to $2m per MW, while for coal power plants, it is between $2m and $3m per MW,” another source in the sector explained.
In December 2022, The PUNCH reported that the Federal Government and the 36 state governors finally agreed to sell five power plants under the National Integrated Power Projects and use the proceeds to fund the 2023 budget.
Parties in the deal reached the agreement in December after over two years of disputes and legal tussle as regards the sale of the NIPP plants being managed by the Niger Delta Power Holding Company.
The NDPHC, owned by the federal, state, and local government councils, is a power generation and distribution company that oversees the implementation of the NIPPs.
The former Director-General, Bureau of Public Enterprises, Alex Okoh, had disclosed the agreement between the Federal Government and the states as regards the NIPP plants to journalists in Abuja during an interview. The disclosure was, however, opposed by various groups.
There have been discussions and plans for the sale of the NIPPs by the Bureau of Public Enterprises for several years, with the specific details and target sale amount evolving over time.
In April 2021, the National Council on Privatisation approved the sale of five NIPPs through a fast-track strategy. The estimated value of these five plants was not publicly disclosed at the time.
In March 2022, the Nigerian National Petroleum Corporation expressed interest in acquiring some NIPPs, indicating continued progress with the sale.
In December 2022, the former BPE boss, Okoh, confirmed an agreement between the Federal Government and states for the sale of five NIPPs.
He projected the sale to generate over N260bn (around $600m). However, some many sources and CSOs expressed concerns that this amount wouldn’t significantly impact the rising budget deficits at the time.
As of today, and going by what the acting DG of the BPE states, the sale of the NIPPs has not been finalised. The Niger Delta Power Holding Company, which manages the NIPPs, has also not confirmed its sale.
Meanwhile, it should be stated that while there is no official confirmation on the cost of the NIPPs, some sources speculate that the initial estimates for individual NIPPs could have ranged from $300m to $500m.